Amazon’s (NASDAQ:AMZN) plan to build a data center powered by a Pennsylvania nuclear power plant has not changed, even as the ...
Talen Energy (TLN) and Amazon (AMZN) shares fell over 2% and 1%, respectively, on Monday. The decline came after the U.S.
Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
The US Federal Energy Regulatory Commission (FERC) has rejected a proposal that would have allowed an Amazon data centre ...
Chairman Willie Phillips dissented from the decision on the “first of its kind” co-location proposal, saying it could harm ...
Discover if Talen Energy (TLN) remains a buy after FERC's Amazon deal block. Analyze key price levels and future prospects.
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into ...
The company’s “foot is on the accelerator” to close data center deals as it works to restart Three Mile Island Unit 1 by 2027 ...
The commission agreed with opponents of the proposal, citing concerns about grid reliability and cost fairness.
Liam Denning is a Bloomberg Opinion columnist covering energy. A former banker, he edited the Wall Street Journal’s Heard on ...
The proposal aimed to revise an ISA involving PJM, the regional grid operator, Susquehanna Nuclear, which owns the power plant, and transmission owner PPL Corp. The amendment would boost the data ...
The Amazon data center is located close to Talen's Susquehanna nuclear power plant in Pennsylvania, as previously reported. The amended interconnection deal would have supplied more power directly ...