Microsoft is canceling its plans to build a data center near the Oak Creek Power Plant after the community rallied against ...
Outcry from residents and elected officials caused Microsoft to drop the Caledonia plan. But the company is seeking an ...
Microsoft cancels its Caledonia, Wisconsin, data center project after community pushback but remains committed to future ...
The tech giant withdraws from 244-acre site near Douglas Avenue while maintaining commitment to Southeast Wisconsin ...
Microsoft is dropping its plans for a data center in Caledonia after facing opposition from residents and some village ...
Microsoft has decided not to move forward with its proposed site for a data center in the Village of Caledonia after facing ...
After petitions and meetings, Microsoft scrapped a 244-acre data center in Caledonia, citing community feedback, and may seek ...
Microsoft is planning to build a backup data center on 244 acres of land in Caledonia. The Village Board needs to approve a ...
The Village of Caledonia will host a community meeting on Monday, Sept. 29 for residents to ask questions and learn more ...
Caledonia officials advanced Microsoft s third Wisconsin data center plan with rezoning approval. So far, Microsoft invested ...
A Caledonia planning commission approved rezoning plans Monday night for a proposed Microsoft artificial intelligence data center. The vote was five in favor, two against. The center would be built on ...
Microsoft and its development partners have cleared their first major hurdle in the approval process for a 244-acre data center in Caledonia. In a 5-2 ...